0
$\begingroup$

A construction company has 6 projects, for each they need $d_i$ workers. The company has no workers at the beginning of project 1.

Each new worker must take a safety course that costs 300, and 50 more for each worker. If there is no new worker there is no course.

Firing a worker does not cost any money, and a workers can't be rehired.

Given that the salary of a worker is 100 per project, formulate a linear programming problem that minimizes the workers costs.

What I tried:

Let $x_i$ be the number of new workers for project $i$.

Let $y_i$ be the number of old workers remaining from previous projects until project $i$ (all the workers hired - all the workers that were fired)

Let $z_i$ be an indicator such that $z_i =0 \iff x_i>0$

The function I'm trying to solve is:

$\min(\sum_{i=1}^6 150x_i + 300(1-z_i) + 100y_i)$

s.t: \begin{align} x_i,y_i,z_i &\ge 0 \\ z_i &\ge 1-x_i \\ y_i + x_i &\ge d_i \\ y_i &\ge y_{i-1} + x_i \end{align}

Something feels not right to me. The main reason is that I tried to use matlab to solve this and it failed.

What did I do wrong? How can I solve this question?

$\endgroup$

1 Answer 1

2
$\begingroup$

Seems correct except that the last constraint should instead be $y_i \le y_{i-1} + x_{i-1}$.

$\endgroup$
0

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.