Twelve men can finish a job in 16 days. 5 men were working at the start and after 8 days, 3 men were added. How many days will it take to finish the whole job?
Solution:
So, the job will take $12 \times 16 = 192$ man days to finish. In the first $8$ days we have done $8 \times 5 = 40$ man days. Now we are doing $8 \times 8 = 64$ man days per day and need to do the remaining $192 - 40 = 152 $man days.
- Day $1 = 152 - 64 = 88$ man days left
- Day $2 = 88 - 64 = 24$
So, we’ll finish on day $3$ after the extra $3$ men are added.
So based on my solution, I came up with $11$ days but I feel like it's wrong. Can someone point out my mistakes if any?