Am doing a math text book, and I came across this one:

120 men can lay a road which is 80km long in 20days. 100 men can lay a road of 90km in how many days?

I tried finding per man = 1/30 km per day; and solving, but it didn't work.

Please help

share|improve this question

2 Answers 2

Imagine $120$ people working on the $80km$ road. We can assume that each person works on a small part of it, such that after 20 days everybody has completed his/her section and the road is complete. Thus, we have the $80 km$ road divided between $120$ persons, and this means that each person lays $\frac{80}{120} km$ of road in 20 days. This also means that the length of road laid down by each person per day is $\frac{1}{20}\cdot \frac{80}{120} km = \frac{1}{30} km$.

Now, we have $100$ persons working on a $90km$ road. Let's first ask ourselves how many kilometers of road the team of $100$ people can lay down each day: it is simply what each can do, times the number of people, that is $100 \cdot \frac{1}{30} km = \frac{10}{3} km$.

Knowing that the team can lay $\frac{10}{3} km$ of road per day means that, during $n$ days, the team can lay $\frac{10}{3} km \cdot n$ of road. Since we want to find $n$ when the team lays $90km$ of road, we state the equality:

$$\frac{10}{3} km \cdot n = 90km$$ Divide by $\frac{10}{3} km$ on both sides and you find $n$, that is the number of days it takes to build the road.

Note: I took the long path here because it is very important to understand properly what we are doing. You can make a drawing of the situation to help you, or try to image in your head a geometric representation of the situation.

share|improve this answer
    
Thank you very much. This was a longer one, but It helped. –  Ramana Jan 16 at 5:31
    
Sorry, I cannot vote up for both answers, because I have only 1 reputation. –  Ramana Jan 16 at 5:32
    
No problem, I'm happy to know it helped! –  Olivier Jan 16 at 5:33

I think the calculation is OK. 1 man in 1 day can lay 1/30 km. Then 100 men in 1 day can lay 100/30 km. 100 men can lay 90 km for 90/(100/30)=(90 x 30)/100=27 days.

share|improve this answer
    
Thankyou very much! It helped a lot! Again, thankyou very much. –  Ramana Jan 16 at 4:46

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.