If:
I can make two tools which would serve the same purpose and:
I need 10 times less time to make first tool but work with this tool is a half time slower than work with the second tool, after what period of time I will get advantage by making the tool with which I will work faster by 2 times (the second tool).

share|improve this question

2 Answers 2

up vote 6 down vote accepted

If it takes $x$ hours to make the first tool then it will take $10x$ hours to make the second tool. Also, if a job takes $y$ hours with the first tool it will take $\frac{1}{2}y$ hours with the second tool. So you are asking when

$$ x+y\geq 10x+\frac{1}{2}y. $$

Rearranging this inequality indicates

$$ y\geq 18x. $$

So, once your job requires at least $18x$ hours, the second tool is better.

share|improve this answer

HINT $\:$ If the slow tool takes $\rm\:T\:$ hours to build, then the fast tool takes an extra $\rm\: 9\ T\:$ hours to build. For the double-speed tool to make up for this lost time in a job of $\rm\ J\ $ hours, its saved time of $\rm\ J/2\ $ hours must equal the lost build time $\rm\ 9\ T\:,\ $ i.e. $\rm\ J/2\ =\ 9\ T\:.$

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.